If I got my calculation right :) . After almost a year working away from home, away from my wife and away from my kids :( , we are finally going live. We are implementing SAP to 4 companies and the first company, will go live in 27 days.

The Project Office did not freeze any leave, but were are told not to make any plans during the Labor Day and throughout that weekend. From now until SAP goes live, I am going to be very busy. That’s why the review on the top commentators of the threesome contest will be a bit late (alasan).

Implementing SAP is expensive. The money spent and the people involve are huge. Some departments, like mine, were reduced to 1/3 of the original manpowers. Too bad that the people who stayed behind have to double their effort.

DCRs (document for change request) are expected to increase in the coming weeks. The functional teams are aggressively testing all standard and localized SAP applications. This has put some pressures to the Abapers, but so far most of them are still maintaining their cool.

Me? I am cool as usual :) .

We have managed to come this far and I really want to see it through. My only hope is that the potential benefits will be able to justify the cost, if not my future annual increments and bonuses will be affected :( OK, not only mine but also the rest of the employees.

Tags: , , , ,

Popularity: 4% [?]

Share and Enjoy: These icons link to social bookmarking sites where readers can share and discover new web pages.
  • Digg
  • del.icio.us
  • De.lirio.us
  • StumbleUpon
  • Furl

More Related Posts